Punjab Proposes Wind, Hydro, Energy Storage Obligation Trajectory Up to FY 2030

The public hearing on the draft policy will be held on November 16, 2022

thumbnail

Punjab State Electricity Regulatory Commission (PSERC) has issued the Draft Punjab State Electricity Regulatory Commission (Renewable Purchase Obligation and its compliance) Regulations, 2022, outlining the renewable purchase obligation (RPO) trajectory for the state up to financial year (FY) 2029-30.

The public hearing on the draft policy will be held on November 16, 2022.

In line with the Ministry of Power’s recently issued RPO trajectory, the Commission has issued the purchase obligations for Wind, Hydro, Energy Storage, and other renewable energy sources.

The table below shows the financial year-wise breakdown for various renewable energy purchase obligations

Punjab Proposed Renewable Purchase Obligation (RPO) Trajectory up to FY 2030

Per the draft regulations, the Wind RPO must be met from energy produced from wind power projects commissioned after March 31, 2022. Wind energy consumed must be over and above 7% from wind projects commissioned until March 31, 2022.

Hydro Power Obligation (HPO) must be met by energy produced, including free power being provided to the state from hydropower projects, including pumped hydro storage projects and small hydropower projects commissioned after March 8, 2019.

Other RPO may be met by energy produced from any renewable power projects except wind and hydropower projects. From financial year (FY) 2022-23 onwards, the energy, including free power being provided to the state from all hydropower projects commissioned till March 8, 2019, will be considered part of RPO under the category of other RPO.

The Energy Storage Obligation (ESO) must be met from solar or wind energy and storage projects and will be treated as fulfilled only when at least 85% of the energy stored in the energy storage system annually is procured from renewable energy sources.

Any shortfall remaining in achieving other RPO categories in a particular year can be met with the excess energy consumed from wind projects commissioned after March 31, 2022, beyond the wind RPO for that year. It can also be met through excess energy consumed from eligible hydropower projects commissioned after March 8, 2019, beyond the HPO that year. Further, any shortfall in achieving wind RPO in a particular year can be met with excess energy consumed from hydropower, which is over HPO for that year and vice versa.

Punjab Energy Development Agency (PEDA) is the recommended state agency for accreditation of eligible entities for grant of certificates and to undertake functions under these regulations.

The state agency must devise an appropriate protocol for collecting and verifying information from various sources such as renewable generating companies, distribution companies, state load despatch centers, or any other agency to compute, reconcile and monitor RPO compliance. The state agency must publish monthly statements on a cumulative basis of RPO compliance by different entities on its website and serve notices to the defaulting obligated entities that have not fulfilled the mandated RPO and have not deposited the penalty.

It must also submit quarterly and annual reports to PSERC by June 30 of the following year regarding the compliance of RPO by entities for the previous year.

An obligated entity failing to fulfill its RPO during any year will be liable to deposit an amount as a penalty within 30 days of the end of the year. The amount will be equivalent to the product of shortfall in RPO compliance and the maximum clearance price of the certificates discovered in the power exchange during the said year. The amount must be remitted into a separate account to be created and maintained by the state agency.

The amount the state agency receives must be transferred to the state transmission utility every quarter to be utilized to develop transmission infrastructure to evacuate or integrate renewable energy as approved by the Commission.

Subscribe to Mercom’s real-time Regulatory Updates to ensure you don’t miss any critical updates from the renewable industry.

RELATED POSTS

Get the most relevant India solar and clean energy news.

Featured
thumbnail
14:46 Installs a Record 2.5 GW of Solar Open Access in 2022, Up 92% YoY

India added 2.5 GW of solar open access in the calendar year (CY) 2022, a year-over-year (YoY) increase of 92% from the 1.3 GW installed in CY 2021, according to the newly released 2022 Q4 & Annual Mercom India Solar Open ...

March 16, 2023

Markets & Policy

25% of Generation Capacity of Coal Plants Must be from Renewables: Ministry of Power

The Ministry of Power (MoP) has proposed that any coal-based thermal generation station coming up after April 1, 2024, must either install or procure renewable energy equivalent to 25% of the thermal generation capacity. Stakehold...

November 9, 2022

Mercom Research Focus

India’s Solar Market Leaders for 1H 2022

Mercom India has released its report, India Solar Market Leaderboard 1H 2022, unveiling solar market leaders in the first half (1H) of the calendar year (CY) 2022. The report covers market share and shipment rankings across the In...

November 9, 2022

Energy Storage

Webinar to Shed Light on How Battery Storage Enhance Solar Systems’ Performance

Battery energy storage technologies globally are transforming how companies utilize, control, and dispatch electricity and facilitating a smoother transition to clean energy. The Indian market is also realizing how battery storage...

November 9, 2022

Magazine

DON'T MISS AN ISSUE!

Mercom Cleantech Magazine

Get Your Copy Today!

magazines

Latest News

Test Video Post2

This is custom content that will be displayed at the video in case you want to give an overview, etc. Michael Ballard

November 30, 2022

thumbnail
14:46 Installs a Record 2.5 GW of Solar Open Access in 2022, Up 92% YoY

India added 2.5 GW of solar open access in the calendar year (CY) 2022, a year-over-year (YoY) increase of 92% from the 1.3 GW installed in CY 2021, according to the newly released 2022 Q4 & Annual Mercom India Solar Open...

March 16, 2023

thumbnail
25% of Generation Capacity of Coal Plants Must be from Renewables: Ministry of Power

The Ministry of Power (MoP) has proposed that any coal-based thermal generation station coming up after April 1, 2024, must either install or procure renewable energy equivalent to 25% of the thermal generation capacity....

November 9, 2022

JANUARY 2023

Some test content that can be displayed somewhere maybe if needed? Not sure Michael Ballard

November 30, 2022

DECEMBER 2022

December 2022 Magazine Post Michael Ballard

March 2, 2023

NOVEMBER 2022

March 2, 2023

Mercom India Renewables Summit 2023

OUR FLAGSHIP EVENT, MERCOM INDIA RENEWABLES SUMMIT, APRIL 2023   Mercom India Renewables Summit 2023 (formerly Mercom India Solar Summit) brings together developers, manufacturers, investors, innovators, and other key decision...

November 28, 2022

thumbnail
PTC India’s EoI to Procure 1 GW of Hybrid Power Receives Overwhelming Response

PTC India’s expression of interest (EoI) to procure 500 MW of hybrid renewable energy (wind and solar) (Tranche-I), with a greenshoe option for an additional 500 MW, has received a strong response, according to Mercom sources....

November 9, 2022

thumbnail
Higher Operating Costs Drive Fuel Cell Firm Ballard’s Net Loss Up 39% YoY in Q3

Ballard Power Systems, a fuel cell and clean energy solutions provider, recorded a net loss of $42.88 million in the third quarter (Q3) of 2022, a year-over-year (YoY) increase of 39%. The revenue for the quarter was $21.34...

November 9, 2022

thumbnail
Solid Power Posts Loss of $12.4 Million in Q3 As Operating Expenses Soar

Solid Power, Inc., a U.S.-based developer of all-solid-state battery cells for electric vehicles (EVs), reported a net loss of $12.4 million for the third quarter (Q3) 2022, a 46% increase from the $8.45 million loss during the...

November 9, 2022

MORE NEWS